Sunday, December 22, 2013

Framing

Once the concrete slab foundation was poured, a lot more action started to happen. The red tubing is for our hydronic radiant heat.
It took about two days to get the basement and part of the the main floor framed.
Checking out the basement digs. We'll eventually ship Layla down here when she's an unruly teenager.
The main floor is almost done. Alex and the crew were great.

No comments:

Post a Comment

Total Pageviews